Masthead

 

 

 

Natural Approaches
to Stormwater Management
Home Page

Island County Stormwater Code LID Requirements

Issaquah Stormwater Management Policy for LID

Lacey Zero-Effect Drainage Discharge Ordinance

Olympia LID Strategy for Green Cove Basin

Pierce County LID Regulations

Snohomish County Reduced Discharge Housing Demonstration Program

Tumwater Zero Effect Development Ordinance

Washington State Department of Transportation, LID in the Highway Runoff Manual

Natural Approaches to Stormwater Management

Ordinances & regulations


Island County Stormwater Code
Low Impact Development Requirements

Background
In December 1998, Island County adopted a stormwater ordinance that provides developers with the option of using low impact development practices. The design standards are based on Low Impact Development Design Strategies—An Integrated Design Approach, prepared by Prince Georges County, Maryland, January 2000.

Description
The Island County Stormwater and Surface Water Ordinance provides special performance requirements that developers must meet for their development proposals to qualify as LID. The code states:

A. Runoff Volume Control. The pre-development volume is maintained by a combination of minimizing the site disturbance from the pre-development to the post development condition and then providing distributed retention BMPs. Retention BMPs are structures that retain the runoff for the design storm event. A “customized” or detailed runoff curve number (CN) evaluation is required to determine the required runoff volume. The storage required to maintain the pre-development volume may also be sufficient to maintain the pre-development peak rate.

B. Peak Runoff Rate Control. Low-impact development is designed to maintain the pre-development peak runoff discharge rate for the selected design storm events. This is done by maintaining the pre-development time of concentration and then using retention and/or detention BMPs (e.g., rain gardens, open drainage systems, etc.) that are distributed throughout the site. The goal is to use retention practices to control runoff volume and, if these retention practices are not sufficient to control the peak runoff rate, to use additional detention practices to control the peak runoff rate.

C. Flow Frequency Duration Control. Since low-impact development is designed to emulate the pre-development hydrologic regime through both volume and peak runoff rate controls, the flow frequency and duration for the post development conditions will be almost identical to those for the pre-development conditions. The impacts on the sediment and erosion and stream habitat potential at downstream reaches can then be minimized.

D. Water Quality Control. Low-impact development is designed to provide water quality treatment control for the duration storm runoff from impervious areas using retention practices. The storage required for water quality control is compared to the storage required to control the increased runoff volume. The greater of the two volumes is the required retention storage. Low-impact development also provides pollution prevention by modifying human activities to reduce the introduction of pollutants into the environment. (Title 11.03)

The ordinance allows applicants who propose to use LID practices for development approvals a choice. Applicants of small development projects may accept permit conditions that fulfill the best management practices for LID surface water rate control in lieu of submitting a drainage narrative. For major development activities and engineered grading projects, applicants who propose to use LID drainage controls may submit a drainage narrative instead of a preliminary drainage plan. The ordinance does not require a downstream analysis when the project design includes and is approved for using LID standards.

To date, LID practices have been partially applied in developments such as Bayview Corner (see page 26), but no major developments have used LID technologies in Island County.

Contact
Phil Cohen
Surface Water Management Division
Island County Public Works

Phone: (360) 679-7331 extension 7440
FAX: (360) 678-4550
philc@co.island.wa.us

Back to top

 

Stormwater Management Policy for Low Impact Development
City of Issaquah

Background
The city of Issaquah is growing rapidly. With annexations, the population could increase from 13,790 today to 47,000 by 2020. Two urban villages alone—Issaquah Highlands and Talus—could add more than 5,000 residential units, 3.5 million square feet of commercial and office space and 500,000 square feet of retail space. This growth will place heavy demands on already limited groundwater supplies, a congested road system and degraded stream ecosystems. Issaquah Creek is a regionally significant stream that provides habitat for the threatened Puget Sound chinook salmon. In 2000, the city of Issaquah adopted an update to the stormwater code (Title 13.28.055) that provides a process and criteria for evaluating low impact development proposals.

Description
The municipal code authorizes the Director of Public Works to authorize deviations from stormwater design standards to achieve “low impervious surface development.” The director also has the option of requiring evaluation and monitoring of project elements. The code language is on the Municipal Research Services Center website (www.mrsc.org). Go to “Legal Resources,” then “City and County Codes,” then “City Codes” to Issaquah City Code Title 13.28.055.

Authorizations for deviation from design standards are to be based on the following criteria. The policy states:

1. The deviations will produce a compensating or comparable result in stormwater flow control and treatment that is in the public interest;

2. The deviations contribute to and are consistent with the goal of achieving low effective impervious surface area within a development;

3. The proposed development project offers reasonable assurances that low impervious surfaces will be achieved and maintained;

4. The deviations do not threaten public health or safety;

5. The deviations are consistent with generally accepted engineering and design practices;

6. The deviations promote one or more of the following:

a. Innovative site or housing design;

b. Increased on-site stormwater retention using native vegetation;

c. Retention of at least 60 percent of natural vegetation conditions over the site;

d. Improved on-site water quality beyond that required by current applicable regulations;

e. Retention or re-creation of pre-development and/or natural hydrologic conditions to the maximum extent possible;

f. The reduction of effective impervious surfaces to the maximum extent practicable;

7. The deviations do not allow density greater than what would otherwise be allowed under city regulations then in effect;

8. The deviations do not present significantly greater maintenance requirements at facilities that will be eventually transferred to public ownership;

9. There shall be submitted in conjunction with each such project, covenants, conditions and restrictions which will be binding upon the property all necessary native growth protection easements, impervious surface restrictions and such other critical features as the Director may require.

The Issaquah Municipal Code (Title 13.30) also provides an incentive for projects that infiltrate stormwater. Projects that infiltrate 100 percent of the stormwater can receive up to a 50 percent reduction in the stormwater utility fee.

On other fronts, the city is considering a more comprehensive sustainable development program, including incentives. Some of these provisions relate directly to LID, such as green streets, green roofs, and pervious pavers.

Contact
Kerry Ritland
City of Issaquah
(425) 837-3410
kerryr@ci.issaquah.wa.us

Back to top

 

Zero Effect Drainage Discharge Ordinance
City of Lacey

* Zero Effect (or Impact) Development (ZID) means a project that adheres to the 60/0 development standard and is constrained by characteristics of a healthy watershed as described in the Salmon in the City Conference Abstracts. “60/0” means 60 percent forest cover preserved /zero effective impervious surface.

Background
In 1999, the Lacey city council enacted a “Zero Effect* Drainage Discharge” ordinance. Lacey, in Thurston County, has a population of 31,000 and an urban growth area of 31 square miles. City officials, understanding that even small increases in runoff can damage area streams, chose to encourage developers to achieve zero discharge of stormwater runoff. This could well be one of the very first ordinances of this kind passed in the nation.

Description
The goal of Lacey’s ordinance is to retain the critical functions of a forest including evapotranspiration and infiltration after site development such that near zero effective impervious surface is achieved. The purposes of the ordinance show that city planners saw this as a new concept that would go through trial and evolution. The ordinance states:

A. Provide those developing land the opportunity to demonstrate zero effective impervious surfaces.

B. Improve the conditions of habitat and ground and surface waters within a watershed with innovative urban residential design and development techniques.

C. Foster broad community acceptance of the use of significantly less impervious surface and greater natural habitat conservation on sites.

D. Provide the opportunity to identify and evaluate potential substantive changes to land use development regulations which support and improve natural functions of watersheds.

The ordinance is flexible and establishes performance standards for development rather than specific design criteria. A committee of Lacey staff has the authority to grant administrative variances from traditional standards to achieve the ordinance’s goal.

Projects must preserve 60 percent natural habitat area and achieve “near zero effective impervious surface.” A variety of practices can contribute to meeting the provisions of the ordinance, such as:

  • Constructing narrower roads without curb and gutter.
  • Using pervious paving systems.
  • Using native forest as the stormwater management system.
  • Avoiding discharges from impervious surfaces to surface streams.

Expected Results
The intent of the ordinance is that projects constructed under this ordinance will eliminate overland flow discharges and have no measurable impact on receiving waters and aquatic life. Such projects will be more aesthetically pleasing, require little or no erosion control during construction, and add value to the city.

Contacts
Eric Hielema
City of Lacey
(360) 438-2686
ehielema@ci.lacey.wa.us

Website: www.wa.gov/lacey/main_menu/main_set.html

Website for Chapter 14.31 Zero Effect Ordinance:
www.wa.gov/lacey/lmc/lmc_main_page.html

Thomas W. Holz
SCA Consulting Group
(360) 493-6002
tholz@scaconsultinggroup.com

Back to top

 

Low Impact Development Strategy for Green Cove Basin
City Of Olympia

Background
Olympia, with a population of 41,000, is a rapidly growing city in Thurston County. Despite a variety of measures enacted in the 1980s and 1990s to increase density and protect environmental quality, the quality and diversity of aquatic habitat in the city continued to decline.

In 1998, Olympia undertook a process to “define the balance between human activities and protecting habitat” in its streams and watersheds. After reviewing all city watersheds, the city council decided to focus on the 2,600-acre Green Cove Creek watershed in west Olympia. In October 2001 the Olympia City Council adopted a unique set of mandatory low impact development regulations to prevent further damage to aquatic habitat from urban development in the Green Cove Basin.

Description
Olympia elected officials and staff went through a three-year process of research, analysis and peer review in designing the program for Green Cove Basin. Following is a summary of the major steps:

  • Consultants developed criteria for evaluating the viability of aquatic habitat in Olympia’s eight watersheds and recommended goals for growth and habitat based on the habitat potential of each basin.
  • A team of scientists, including hydrologists and biologists, reviewed and concurred with the consultant’s recommendations.
  • The city council agreed to use the recommended approach in the Green Cove Basin as a pilot project and adopted interim standards for zoning density, stormwater management, timing of clearing and grading, and tree removal.
  • Consultants developed alternate site plans for two proposed developments in the basin to determine whether they could achieve low impact objectives. The city also consulted with realtors, development engineers, bankers, and developers on the site plans.
  • The science team reviewed the standards and proposed designs and confirmed that the proposed subdivision designs were generally consistent with scientific findings and that implementation would have the potential to maintain habitat conditions equivalent to the present.

Based on the above process, the Olympia City Council completed a comprehensive policy revision covering development density, impervious surface coverage, lot size, open space/tree retention, street design, street width, block sizes, parking, sidewalks, and stormwater management requirements. The following is an outline of key policy changes for the Green Cove Basin.

Comprehensive Plan Amendments

  • Designate Green Cove Creek as a sensitive drainage basin.
  • Avoid high-density development where new development would have a significant adverse impact upon the habitat within designated sensitive drainage basins.
  • Administer development regulations that protect critical areas and designated sensitive drainage basins.
  • Adopt low impact development regulations within designated sensitive drainage basins that may include stormwater standards, critical area regulations, zoning designations and other development standards.
  • Establish street designs that minimize impacts to the natural environment especially within a designated sensitive drainage basin.

Olympia Municipal Code

  • Establish a new zoning district with increased tree protection and replacement requirements.
  • Establish residential densities of two to four units per acre; allow duplexes, townhouses, and multifamily uses.
  • Reduce lot widths and rear setbacks and increase maximum building heights compared to other residential districts.
  • Limit maximum impervious surface coverage per lot to 2,500 square feet.
  • Allow several land uses, including duplexes and parking lots that are not typically permitted in single-family residential developments.
  • Require a minimum tree density of 220 trees per acre (approximately 55 percent tree cover in any given development).

Development Guidelines and Public Works Standards

  • Residential block perimeters cannot exceed 1,700 feet.
  • Driveways and sidewalks can be constructed of pervious surfaces with city approval.
  • Sidewalks are required on one side of local access streets.
  • Sidewalk planter widths can be increased from the required eight feet to an optional 25 feet.
  • Additional parking within low impact developments can be provided by the construction of pervious surface lots subject to city approval.
  • A rock infiltration gallery/conveyance system is to be constructed when street slopes are 5 percent or less.
  • Neighborhood collector streets are to be 25 feet wide, with parking provided on alternating sides of the street.
  • Local access streets are to be 18 feet wide, with similar parking arrangements.

Drainage Design and Erosion Control Manual

  • Stormwater discharge must be controlled by matching developed discharge durations to pre-developed durations, for the range of pre-developed discharge rates from 50 percent of the two-year peak flow to the 50-year peak flow.
  • The city will allow clearing and grading within the basin only between May 1 and October 1 of any given year.

Since part of the Green Cove Basin is in Thurston County, the county adopted policy and regulatory changes to complement Olympia’s program. This included changes to the county’s comprehensive plan, zoning, and open space program.

Unlike LID ordinances in Lacey and Tumwater that are voluntary, Olympia’s Green Cove regulations are mandatory. As of October 2002, the city has received two subdivision projects for development under the new policies.

Challenges
Several questions remain unresolved in the Green Cove basin process. The extra costs of non-standard development techniques have not been defined. One question is whether home buyers will buy homes in a “low impact” neighborhood with narrower streets, less parking, smaller home footprints, and regulatory limits to additions that would increase impervious surfaces. Finally, there are still questions about the environmental benefits of the development restrictions, given the overall pattern of development and previous disruption of the natural hydrology.

Contact
Andy Haub
City of Olympia Public Works
(360) 753-8475
ahaub@ci.olympia.wa.us

For a more detailed case study and a CD-ROM containing project reports and ordinances, contact the City of Olympia.

Back to top

 

Low Impact Development Regulations
Pierce County

  Pierce County LID techniques
Select photo to view in larger scale
Example of a site design using LID techniques.
 

Background
Unincorporated Pierce County has a population of 330,000 and a land area of 1,790 square miles. The county is exploring the use of low impact development techniques as a method to maintain natural hydrologic functions during the land development process and reduce impacts associated with conventional stormwater management methods. County staff is evaluating various LID methods for quality of performance and applicability. Development of an LID chapter within the county’s Stormwater and Site Development Regulations will clarify what LID techniques are acceptable and will establish a performance goal and objectives. This chapter will also provide certainty to land developers and federal and state agencies in terms of performance measures and compliance with National Pollutant Discharge Elimination System requirements.

Description
Pierce County, in cooperation with Washington State University Cooperative Extension, is currently developing an LID chapter for the Stormwater Management and Site Development Regulations. A committee review of the proposal was underway at the time of this writing in late 2002.

The following draft chapter establishes a performance goal and objectives and prescriptive standards for LID.

The goal of Low Impact Development is to manage stormwater generated from new development and redevelopment so there will be no negative impacts to adjacent and/or downstream property owners and no degradation to groundwater or surface waters such as but not limited to streams, ravines, wetlands, potholes, and rivers.

The Low Impact Development goal shall be achieved through adherence to the following objectives:

  • Maintain and/or restore the pre-developed, undisturbed stormwater flow volumes, flow frequencies and durations, and water quality from a developed site. In the Puget Sound lowlands, the predeveloped hydrologic condition is near zero overland flow runoff. (Note: To provide a quantifiable and measurable standard for flow control, minimum requirement #7 Flow Control of the Department of Ecology Stormwater Management Manual for Western Washington, will be adhered to in addition to meeting the other objectives listed below. It states that stormwater discharges shall match developed discharge durations to predeveloped durations for the range of predeveloped discharge rates from 50% of the 2-year peak flow up to the full 50 year peak flow.)
  • Establish the pre-developed condition of a site used for hydrologic modeling as the native vegetation and soils that existed on the site prior to 1800 A.D., which shall be a forested land cover unless reasonable, historic information indicates the site was prairie prior to settlement (modeled as “pasture” in the Western Washington Hydrology Model.)
  • Retain or restore native soils and vegetation on 65% of the site area. Where 65% is not achieved the applicant will demonstrate how the combined use of other LID techniques will achieve the overall goal.
  • Limit the effective impervious area of the site to no more than 10%.
  • Retain and incorporate natural site features that promote infiltration of stormwater on a developed site.
  • The use of traditional conveyance and pond technologies to manage stormwater quality and quantity should only be considered after all other LID techniques have been considered and used to the greatest extent possible.
  • Use bioretention, pervious surfaces, open space surface water dispersion, soil restoration, and other dispersed facilities to control stormwater as close to the origin as possible.

To meet the goal and objectives, the draft chapter discusses how LID can be considered at each phase of development including: site planning; vegetation retention and reforestation; site clearing and grading; roads, parking and sidewalks; and building design. It also provides best management practices and monitoring requirements. In addition, the chapter will address ongoing management and maintenance needs, and education of homeowners.

Pierce County, in cooperation with Washington State Cooperative Extension, has entered into a partnership with a private developer to develop an LID pilot project. For more information on this project, see Meadow on the Hylebos, page 32, or call Len Zickler, AHBL, at (253) 383-2422.

Contacts
Katherine Brooks
Pierce County, Planning & Land Services
(253) 798-3181
kbrooks@co.pierce.wa.us

Hans Hunger
Pierce County Public Works and Utilities Water Programs
(253) 798-6162
hhunger@co.pierce.wa.us

Website: www.co.pierce.wa.us/pc/services/home/property/pals/landuse/esa.htm
(see Title 17A amendments)

Back to top



Reduced Discharge Housing Demonstration Program
Snohomish County

Background
In the 1990s, Snohomish County, with a population of 628,000, established a program to introduce different development schemes, such as mixed use, affordable housing and innovative designs. As part of this effort, the county adopted the Reduced Discharge Housing Demonstration Program (Ordinance 00-004) in April 2000. This program provides a three-year trial period for selecting and overseeing demonstration low impact development projects.

Description
The reduced discharge ordinance has five purposes:

  1. Demonstrate the benefits of alternative development practices that reduce offsite discharge.
  2. Improve the conditions of habitat, ground and surface waters.
  3. Foster community acceptance of housing that conserves habitat and uses less impervious surface.
  4. Allow flexibility in the development standards.
  5. Identify and evaluate desirable changes to the land use code.

Requirements and guidelines in the ordinance provide for a variety of LID concepts, such as infiltration, tree retention, density bonuses, smaller footprints/taller house designs, permeable pavements, grass pavers, and minimizing grading and site disturbance.

The county established a special committee to oversee the program, select demonstration sites and recommend changes to the land use code. The committee includes representatives of county departments, environmental organizations, university faculty, and the development community. The committee began its work with a tour of low and reduced impact development sites in Snohomish and King counties. Snohomish County sites included the Canyon Park Business Center (which uses bioswales for water quality treatment and groundwater recharge) and the Harbor Point Master Planned Community (which recharges groundwater through a wetland).

To guide submittal of development proposals, the committee developed an outline of minimum requirements and a project review checklist (available from the county on request). By the end of 2002, developers had proposed six project design concepts. The county accepted three of these projects into the system. The project rating system evaluates tree retention (minimum 60 percent of the site); impervious surfaces; infiltration (minimum 70 percent); visual impact; innovation; and the reputation of the developer.

One project proposal is for higher-end fourplex condominiums. The site is heavily forested with steep slopes and outwash soils. A vertical design with underground parking and narrower roads will save tree cover and reduce runoff. Permeable pavement will reduce impervious cover and soils will be amended with compost. The county will need to modify the zoning code from the current single-family classification to allow for this type of development in this area.

The second proposal, Wandering Creek, is for lower cost single-family housing. The site is bounded by wetlands on three sides. The upland area is on outwash soils and will drain to a wetland buffer. LID features include preserving overstory vegetation, working with topography, narrowing the road section, using permeable pavers, and reducing building footprints to 1,000 square feet.

A third proposal is in an existing plat where the developer proposes to revegetate a pasture area with trees.

County staff and the developers will jointly monitor each of the development projects for stormwater flows. Results will be available to the public once construction begins.

Challenges
The county’s demonstration program has faced several challenges in implementation. Developers and engineers have proven reluctant to try new approaches and techniques. They also state that the Department of Ecology’s Stormwater Management Manual for Western Washington limits the use of wetlands for infiltration.

Costs
Cost estimates for these LID projects are highly variable and site-dependent. The fourplex project on a steep slope will be expensive due to the vertical design and underground parking, but the site would be difficult to develop without the flexibility provided under the LID program. The single-family housing project is expected to be less expensive than a traditional development because of reduced road width and sidewalks on one side of roads. The developer is also receiving a density bonus, which allows him to add several housing units on the site.

Contact
Randy Sleight
Snohomish County Planning and Development Services
(425) 388-3424 extension 2014
randy.sleight@co.snohomish.wa.us

Back to top

 

Zero Effect Development Ordinance
City of Tumwater

  *Zero Impact Development means a project that adheres to the 65/0 (65 percent forest cover preserved / zero effective impervious surface) development standard and is constrained by characteristics of a healthy watershed as described in the Salmon in the City Conference Abstracts.
 

Background
The city of Tumwater in Thurston County has a population of 12,730 and an area of 10.7 square miles. Several years ago, city officials and staff recognized the relationship between traditional development practices and stream degradation, and established alternative development standards to protect aquatic life in receiving waters.

Description
In 2000, Tumwater enacted the Zero Effect Drainage Ordinance (Title 13, Chapter 13.22). The city found that typical site development hinders stormwater retention, that stormwater discharges offsite adversely affect stream habitat, and that retaining forest canopy aids evapotranspiration and infiltration of stormwater runoff. The ordinance provides developers with the option of using zero impact development* practices in residential and commercial projects. A set of performance guidelines indicates the characteristics of an acceptable project.

While the ordinance contains design guidance it also allows design creativity. A committee reviews project proposals and can approve variances to the city’s development code to accommodate nontraditional construction techniques. Projects approved under the ordinance must preserve 65 percent of forest area on the development site. Runoff must not be collected or discharged to surface water (thus achieving zero effective impervious area). The guidelines encourage looped one-way streets; narrow pervious driveways; small, pervious garage aprons; and small home footprints. Roof runoff must be infiltrated or mitigated. To compensate for narrower roads and reduced access for emergency vehicles, structures are required to meet more rigorous fire standards.

Costs
There is the potential for substantial cost savings for projects that might be approved under this ordinance, however no cost analysis was performed.

Contacts
Michael Matlock
City of Tumwater
(360) 754-4210

Website:
www.ci.tumwater.wa.us/
Follow the link to City Departments,
then Planning and Facilities.

Thomas W. Holz
SCA Consulting Group
(360) 493-6002
tholz@scaconsultinggroup.com

Back to top

 

Low Impact Development in the Highway Runoff Manual
Washington State Department of Transportation

  Workers install Eco-Stone® permeable pavers
Select photo to view in larger scale
Workers install Eco-Stone® permeable pavers at a municipal park and ride in Marysville. The Washington State Department of Transportation is considering using permeable pavement, such as Eco-Stone®, at its park and rides and on pedestrian paths.
 
Eco-Stone® permeable pavers
Select photo to view in larger scale
Eco-stone detail
 

Description
The Washington State Department of Transportation is currently revising its 1995 Highway Runoff Manual. As part of this revision, the department will develop and reference three low impact development elements in the revised manual:

1. Permeable paving at park and rides, pedestrian paths, and lower speed roadways.

2. Bioretention along roadways.

3. Constructed wetlands for stormwater treatment.

The LID portion of the revised manual should be available for use by the end of September 2003 and will include plans, specifications, methodology for estimating costs, and a hydraulic design process.

Contacts
Rick Johnson

Washington State Department of Transportation
(260) 440-4642
johnsor@wsdot.wa.gov

Larry Schaffner
Washington State Department of Transportation
(360) 570-6657
schaffl@wsdot.wa.gov
Website:
www.wsdot.wa.gov/fasc/
Follow the links to:

>Engineering Publications
>On-Line Technical Manual Library
>Highway Runoff Manua

Back to top

 

Puget Sound Action Team
Office of the Governor
P.O. Box 40900, Olympia, Washington 98504-0900
Toll-free (Washington only): (800) 54-SOUND, Outside Washington (360) 725-5444

PRIVACY NOTICE
Comments or problems with this page? Contact webmaster.
Copyright © August 10, 2000 All Rights Reserved